2 November 2023
Energy and Resource Markets Branch
Ministry of Business, Innovation and Employment
By email: offshorerenewables@mbie.govt.nz
Developing a Regulatory Framework for Offshore Renewable Energy
Meridian is New Zealand's largest generator of renewable energy and operates six large hydro stations and five large wind farms. We have a sixth wind farm and a grid scale battery currently under construction. Since we were established Meridian has:
- invested $5 billion in new renewable generation projects;
- created 5,200GWh of new renewable generation;
- produced enough new renewable electricity to:
- enable the removal of the equivalent of 2.2 - 5.2 million tonnes of CO2 annually from the global atmosphere, compared to GHG emitting alternatives; or
- enable removal of 1.2 - 2.8 million light fleet vehicles from the road; or o meet the energy needs of 715,000 households.
Meridian appreciates the opportunity to comment on the Government's second discussion document on the development of a regulatory framework for offshore renewable energy. Nothing in this submission is confidential.
Meridian has signed a memorandum of understanding with Parkwind for the exploration of offshore wind generation in New Zealand waters. Efforts will focus principally on the Taranaki coast and build on work already undertaken by Parkwind, including engagement with the iwi of Taranaki and key stakeholders. Depending on the outcome of the joint exploration, the two parties may decide to work towards a feasibility permit. Both parties are interested in long- term investments and relationships, following a build to own and operate business model.
Meridian Energy Limited | 293-297 Durham St North | Phone 8088 496 496 |
P O Box 2128 Christchurch | www.meridianenergy.co.nz | |
Christchurch | New Zealand |
To date Meridian has been focused on onshore development given the lower levelized cost of energy. However, the economics of offshore developments may improve over time and as New Zealand's leading wind farm developer, we feel the time is right to learn more about the offshore potential and explore how this might add value to our portfolio.
Parkwind and its parent company Jera (one of the world's largest generation companies) have a strong track record in developing, financing, constructing and operating offshore wind farms. The companies operate seven offshore wind farms off the Belgian, German, UK and Taiwanese coasts, with one of Japan's first offshore wind farms (Ishikari Bay) currently under construction.
While it is unclear at this stage whether offshore development will be economic in New Zealand relative to onshore alternatives, Meridian supports the development of a regulatory regime to accommodate any future investment. Meridian considers the regime should take a developer-led approach to both feasibility and commercial activities.
Appended are Meridian's responses to the detailed design questions in the discussion document.
We would be happy to discuss the views in this submission with Ministers and officials.
Nāku noa, nā
Sam Fleming
Manager - Regulatory and Government Relations
2
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
Appendix A: Responses to consultation questions
Question | Response | |||||
1. | Following an initial feasibility permit | Yes. | ||||
application round, should there be | ||||||
both an open-door policy and the | ||||||
ability for government to run | ||||||
subsequent rounds? If not, why not? | ||||||
2. | What size of offshore renewable | This is a commercial question to be | ||||
energy projects do you think are | considered by any potential developer and | |||||
appropriate for a New Zealand | may change over time as the electricity | |||||
context? | ||||||
market evolves. | ||||||
3. | Do you think the maximum size of a | Maximum project size should not be | ||||
project should be put forward by | prescribed in legislation - guidance can be | |||||
developers and set out in guidance | given and the criteria should be robust | |||||
material, rather than prescribed in | enough to ensure projects are feasible. The | |||||
legislation? If not, why not? | characteristics of a feasible project are likely | |||||
to change over the lifetime of the legislation | ||||||
and any statement on project size could | ||||||
quickly become outdated and a barrier to | ||||||
development. Project viability would be | ||||||
affected if constraints during feasibility stage | ||||||
reduce area and therefore capacity. | ||||||
4. | Should there be a mechanism for | Meridian supports a developer-led, non- | ||||
government to be able to compare | comparative process at the commercial | |||||
projects at the commercial stage in | stage. Comparisons should only be carried | |||||
certain circumstances? If yes, would | out at the feasibility stage. Once a feasibility | |||||
the approach outlined in Option 2 be | permit has been secured investors should | |||||
appropriate or would there be other | have confidence in the pathway to | |||||
ways to achieve this same effect? | commercialisation. Investor confidence will | |||||
be significantly limited if there is a | ||||||
mechanism for competing projects to slow | ||||||
and disrupt progress to commercialisation. | ||||||
All potential developers in a wide geographic | ||||||
area (e.g. Taranaki) will be commercially | ||||||
interested in the extent and likelihood of | ||||||
other development as the volume of | ||||||
expected wind generation concentrated in | ||||||
an area will impact on forecast nodal price | ||||||
outcomes, price participation, and ultimately | ||||||
revenues for any project. The commercial | ||||||
risks associated with other nearby projects | ||||||
3 |
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
should not give any developer grounds to | ||
slow or disrupt competing projects. | ||
5. | Are the proposed criteria appropriate | The types of criteria contemplated in the |
and complete? If not, what are we | discussion document seem broadly | |
missing? | appropriate. However, they are described | |
as considerations for a decision-maker on a | ||
permit application, and not as criteria to be | ||
met by a developer. | ||
Developers would have increased certainty if | ||
is clear what they need to do or demonstrate | ||
in order to pass the assessment for each | ||
criteria, and how the overall assessment and | ||
permit decision will be made, for example is | ||
it a points-based assessment and/or are | ||
there elements that must be passed to the | ||
satisfaction of the decision-maker. | ||
6. | Should there be mechanisms to | Such mechanisms would be appropriate |
ensure developers deliver on the | during the development of a project but once | |
commitments of their application over | a generation site is powered it would be | |
the life of the project? If yes, what | onerous to require ongoing reporting for the | |
should these mechanisms be? | life of the asset. | |
7. | Is 40 years an appropriate maximum | Yes. In addition, a developer should be able |
commercial permit duration? If not, | to apply for a further commercial permit for | |
what would be an appropriate | repowering and continuing to operate at an | |
duration? | existing site. | |
8. | Should a developer that wishes to | Yes. |
geographically extend their | ||
development be required to lodge new | ||
feasibility permit and commercial | ||
permit applications? Why or why not? | ||
9. | Would the structure of the feasibility | Research and development and |
and commercial permit process as | demonstration projects should be enabled | |
described enable research and | under a feasibility permit. | |
development and demonstration | ||
projects to go ahead? If not, why not? | ||
10. | Is there an interdependency between | Yes. One would be a revenue stream for a |
the case for revenue support | project and the other would be a cost. In | |
mechanisms and the decision as to | both cases the Crown would be the | |
whether to gather revenue from the | counterparty and the revenue and cost | |
regime? What is the nature of this | would net out for both parties. The simplest | |
interdependency? | form of support would be to not impose | |
added royalty costs. | ||
4 |
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
11. | Is there a risk in offering support | Meridian opposes financial support |
mechanisms for offshore renewables | mechanisms for offshore renewable | |
without offering equivalent support to | generation (or, for that matter, for any form | |
onshore renewables? Are there any | of renewable generation). | |
characteristics of offshore renewables | It is not clear what problem public financial | |
which mean they require support that | ||
onshore renewables do not? | support would be trying to solve. There is | |
massive renewable electricity generation | ||
investment occurring from both incumbents | ||
and new entrants without any public financial | ||
support. Subsidies in any form (including to | ||
provide revenue stability) would be a cost to | ||
taxpayers that delivered no net gain in | ||
renewable generation. The subsidised | ||
generation would simply displace other | ||
economic options that would have been built | ||
anyway without any support. | ||
Subsidies also risk further market distortions | ||
that then require further interventions to | ||
correct. For example, in Australia | ||
subsidised rooftop solar resulted in very low | ||
or negative daytime prices, and | ||
subsequently challenges for the economics | ||
of firm thermal generation and security of | ||
electricity supply. | ||
A lack of generation subsidies has long been | ||
a strength of the New Zealand electricity | ||
market and as generators we are proud to | ||
deliver investment free of subsidy to meet | ||
demand at least cost. | ||
To the extent developers need revenue | ||
stability, for example in order to gain project | ||
financing, then there are commercial | ||
mechanisms that can be explored such as | ||
PPAs. For well-resourced businesses, | ||
intermittency of generation and revenue is | ||
less likely to be a concern, particularly when | ||
a project forms part of a wider generation | ||
portfolio. | ||
12. | Should there be a revenue flow back | Offshore projects would occupy public space |
to government? And, if yes, do you | rather than private land. Royalty revenues | |
have views on how this should | for the Crown may be reasonable and could | |
optimally be structured? | be equivalent to the land acquisition or | |
access costs for onshore developments. | ||
However, the impact of royalties on project | ||
economics must be carefully assessed. | ||
Royalties should reasonably reflect use of | ||
5
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
public resources without overly deterring | ||
investment. | ||
13. | Do you agree with the proposed | Yes. |
approach to cost recovery? If not, why | ||
not? | ||
14. | Is there anything you would like us to | Iwi, hapū, and whānau will be best placed to |
consider as we engage with iwi and | comment. | |
hapū on Māori involvement in the | ||
permitting regime? | ||
15. | Have we identified the key design | Iwi, hapū, and whānau will be best placed to |
opportunities to work collaboratively | comment | |
with iwi and hapū alongside | ||
consultation? Is there anything we | ||
have missed? | ||
16. | Are there any Māori groups we should | Iwi, hapū, and whānau will be best placed to |
engage with (who may not have | comment | |
already engaged)? | ||
17. | For each individual development, | Meridian is comfortable with the status quo |
should a single consent authority be | where there is the ability to make a joint | |
responsible for environmental | application with the process administered by | |
consents under the RMA and the EEZ | the EPA and ministerial power to establish a | |
Act? Why or why not? | Board if Inquiry to consider the application in | |
its entirety. | ||
18. | Do environmental consenting | Yes. |
processes adequately consider | ||
environmental effects such that it is | ||
not necessary to duplicate an | ||
assessment of environmental effects | ||
in the offshore renewables permitting | ||
regime? | ||
19. | Should the offshore permitting regime | See our response to question 20 below. |
assess the capability of a developer to | ||
obtain the necessary environmental | ||
consents? If not, why not? | ||
20. | What is the optimum sequencing | The optimal sequencing would be for |
between obtaining feasibility permits, | environmental consents to be obtained | |
commercial permits and relevant | before a commercial permit, i.e. | |
environmental consent(s)? | environmental consents could be a pre- | |
requisite to the granting of a commercial | ||
permit. The two could overlap somewhat to | ||
expedite a project but the environmental | ||
6 |
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
consent should be granted first. This would | ||
mean the decision-maker for the commercial | ||
permit would not need to consider | ||
environmental matters or the ability of the | ||
developer to obtain environmental consents, | ||
reducing duplication of effort and costs to | ||
both the developer and the government. | ||
21. | Are there are any other matters about | The offshore permitting regime should not |
the environmental consent regimes | duplicate environmental considerations. | |
that you think need to be considered in | Meridian agrees that there may be value in | |
the context of the offshore renewable | ||
energy permitting regime? | expanding the scope of the National Policy | |
Statement on Renewable Electricity | ||
Generation (or any equivalent in the National | ||
Planning Framework) so that the importance | ||
of renewable generation to the achievement | ||
of national emission reduction goals is | ||
recognised in environmental decision | ||
making under the EEZ regime as well as | ||
within territorial waters. | ||
22. | How should the factors outlined | In Meridian's opinion the regime should be |
influence decisions to pursue offshore | open to developer-led projects in both the | |
renewable energy developments in the | territorial waters of New Zealand and the | |
EEZ or the Territorial Sea? Are there | EEZ. | |
other factors that may drive | Feasibility work by developers will identify | |
development in the EEZ versus the | ||
Territorial Sea? | the most economic, and low risk sites for | |
environmental consenting. | ||
Environmental impacts and competing uses | ||
are not likely to be distinctly different on one | ||
side of the marine boundary compared to | ||
the other. There is likely to be just as much | ||
variability within each area. Certainty the | ||
natural environment does not conform to | ||
jurisdictional boundaries. | ||
23. | Are the trade-offs between a | Meridian supports a developer-led approach |
developer-led and a TSO-led | to give developers more control and | |
approach, set out above, correct? Is | confidence regarding cost and timeframes. | |
there anything missing? What could | Under a TSO-led approach, we would not | |
we learn from international models? | ||
expect transmission infrastructure to be | ||
publicly funded like the Netherlands, rather it | ||
would be Transpower capital expenditure | ||
that would be recovered from the connection | ||
customer over the life of the asset. Public | ||
funding of transmission would be a separate | ||
7
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
consideration as it would be a form of | ||
subsidy for offshore projects. | ||
Developer-led projects would still need to | ||
connect to the grid at an onshore grid | ||
injection point. The current Transpower | ||
connection queue could be a barrier for | ||
projects as investment decisions may not be | ||
made in the absence of confirmed grid | ||
access in a timely manner. Transpower | ||
states that the current connection queue | ||
process is for projects up to 500MW. | ||
However, bespoke connection arrangements | ||
may also need to be considered for offshore | ||
projects smaller than 500MW. | ||
24 | Which party do you think should build | Development and construction of offshore |
offshore connection assets? Can | connection assets should be developer-led. | |
existing processes already provide the | The assets could be operated and owned by | |
flexibility for this to be carried out by | developers by designating the connection | |
the developer? | point at the onshore substation. Giving | |
ownership and operation of multiple offshore | ||
transmission assets to Transpower adds risk | ||
to developers and significant additional | ||
operational risk for Transpower. | ||
In Meridian's opinion existing processes | ||
provide the flexibility for offshore connection | ||
assets to be built and maintained by | ||
developers. | ||
25. | What are the potential benefits and | We agree there may be potential benefit in |
opportunities for joint connection | joint connection infrastructure and that | |
infrastructure? Do you agree with the | developers could reach commercial | |
barriers set out and how could these | agreements to reduce overall costs. | |
be addressed? | However, the barrier identified will make this | |
challenging as will the added complexity of | ||
competitors undertaking collaborative | ||
activities while remaining in compliance with | ||
the Commerce Act. | ||
These are barriers for developers to | ||
consider and overcome where the identified | ||
benefits of joint connection infrastructure | ||
outweigh the costs. We do not see a role for | ||
the Government. | ||
26. | Do you agree with the representation | These challenges also exist for onshore |
of the timeline challenge for onshore | generation developers and incentivise | |
interconnection assets? What | generation investment that most efficiently | |
opportunities might there be to front | utilises the grid. If developers want to | |
load planning work for interconnection | accelerate work on interconnection | |
8 |
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
upgrades? What role do you see for | upgrades this should be achievable on | |
the developer in this? | commercial terms. For example, in 2019 | |
Meridian and Contact entered into | ||
commercial agreements with Transpower to | ||
expedite work on the Clutha Upper Waitaki | ||
Lines Project and reduce transmission | ||
constraints in the event of a smelter exit. | ||
Similar arrangements could be agreed with | ||
an offshore developer to expedite | ||
interconnection works. However, | ||
Commerce Commission approval for any | ||
major capital expenditure would also be | ||
required. | ||
27. | What changes might be needed in | Developers would need to consider this |
order to deliver the types of port | challenge and come to commercial | |
infrastructure upgrades needed to | agreements with ports regarding any | |
support offshore renewables? | changes necessary to meet their needs. | |
28. | Should developers be required to | Yes. |
submit a decommissioning plan, cost | ||
estimate and provide a financial | ||
security for the cost estimate? If not, | ||
why not? | ||
29. | Should the decommissioning plan, | In other jurisdictions, regulations allow |
cost estimate and financial security be | developers to agree alternatives to full | |
based on the assumption of full | removal based on minimising environmental | |
removal? | effects. | |
There is a risk of high levels of | ||
environmental damage during removal of | ||
buried elements (cables and foundation | ||
structures). Decommissioning should follow | ||
a best practice plan agreed by the | ||
environmental consenting authorities. The | ||
decommissioning plan, cost estimates, and | ||
financial security should be based on this | ||
consented best practice plan too, rather than | ||
require full removal at greater harm to the | ||
environment. | ||
This may just be a definitional question of | ||
what is meant by "full removal" under the | ||
proposed regime. | ||
30. | What are your views on the | The considerations in the paper on cost |
considerations set out in relation to the | calculation and financial security vehicles | |
calculation of the cost estimate and | seem reasonable. | |
financial security value or suggested | ||
approach for financial security vehicle? | ||
9 |
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
In Meridian's opinion bank securities would | ||
be the vehicle most likely used by | ||
developers. | ||
31. | What should the developer be required | Meridian agrees that a feasibility application |
to provide in relation to | should demonstrate an initial indicative | |
decommissioning at the feasibility | understanding of decommissioning | |
application stage? | requirements, capability and experience to | |
execute on those requirements, and plans to | ||
work towards a full decommissioning plan at | ||
a later stage. In addition, concrete | ||
decommissioning plans and security | ||
requirements should be included in a | ||
feasibility application to the extent that | ||
structures would be established during the | ||
feasibility stage (for example for research | ||
and development or demonstration projects). | ||
32. | What ongoing monitoring approach do | Given the conservatism and inflation |
you think is appropriate for the | adjustments built into the proposed initial | |
decommissioning plan, cost estimate | cost assumptions, it may be that a less | |
and financial security? | onerous approach could be considered. For | |
example, a review every five years with the | ||
option for ad hoc reviews initiated by the | ||
Government when it becomes aware of | ||
material changes. | ||
33. | Are there any other ways in which the | Decommissioning plans should not be time |
regulatory regime could encourage the | bound and there should absolutely be scope | |
refurbishment of infrastructure or the | to delay decommissioning to facilitate | |
recycling of materials? | extensions to the economic life of offshore | |
generation. | ||
Extensions to commercial permits should be | ||
allowed on the same terms as the initial | ||
commercial permit. | ||
34. | Should offshore renewable energy | Yes. |
projects applying for a consent to | ||
decommission be required to provide a | ||
detailed decommissioning plan related | ||
to environmental effects for approval | ||
by consent authorities? | ||
35. | How can the design of the regulatory | Meridian agrees that the VADE model |
regime encourage compliance so as to | should be followed and that easily | |
reduce instances of non-compliance? | understood rules and guidance will be the | |
key enablers of compliance. | ||
10
Meridian Submission - Developing a Regulatory Framework for Offshore Renewable Energy - 2 November 2023
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Meridian Energy Limited published this content on 23 November 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 23 November 2023 22:25:03 UTC.