  • Assay results returned for first 4 diamond holes drilled by Falcon at Karri with highlights including:

    • o PHKADD018: 2m @ 3.32 g/t Au from 108m including 1m @ 6.51 g/t Au from 109m

    • o PHKADD021: 8m @ 1.09 g/t Au from 287m including 1m @ 7.31 g/t Au from 294m

  • Results show a possible strengthening of alteration and mineralisation in central Karri which is presently being followed up with an additional step-out hole to the north targeting the mineralised east dipping limb 100m down plunge

  • Aircore drilling underway at the Ironbark East Prospect:

    • o Initial holes planned along strike and adjacent to previous intercepts from wide-spaced reconnaissance drilling including 13m @ 1.52 g/t Au (ending in mineralisation)

  • New prospective 872km2 Exploration Licence granted 80km south of Bendigo, which includes areas of outcropping Castlemaine Group sediments with virtually no modern-day systematic gold exploration

  • Falcon remains exceptionally well-funded to continue its large-scale exploration programs in Victoria with >$26 million in cash

Falcon Metals Limited (ASX: FAL) ("Falcon" or "the Company") advises that it has received assay results for the first four diamond holes it has drilled at the Karri prospect in the Pyramid Hill Gold Project, north of Bendigo in Victoria, Australia. Diamond drilling commenced mid-January within a month of listing on the ASX at the Karri prospect, a 4km-long gold anomaly under Murray Basin cover defined by previous aircore drilling. Falcon has completed 7 diamond holes for 2,832m thus far, with assays finalised for 4 of these holes.

Drilling is underway to the north of hole PHKADD021 where the zones of alteration and mineralisation appear to be improving along an anticline and eastern limb. Assay results for the remaining holes will be announced once received and finalised. Whilst one diamond drilling rig is continuing at Karri, the second diamond rig has now commenced drilling at the Ironbark North prospect, ~20km to the south.

Falcon also commenced aircore drilling in late March at the high priority Ironbark East prospect, and soil sampling programs have been initiated across the greater Pyramid Hill project area.

The Pyramid Hill Gold Project has also expanded with the successful granting of Exploration Licence EL07200, a prospective 872km2 exploration permit 80km south of Bendigo.

Falcon Metals' Managing Director Tim Markwell said:

"Falcon is pleased to present its first results from the Karri diamond drilling program, and we are encouraged by the zones of mineralisation being returned and the amount of alteration and quartz veining evident in the drill core. Karri appears to be a large mineralised system, and we are increasingly encouraged about its potential as we continue to scope out the system. Diamond drilling continues and we look forward to releasing more results over the coming months.

Falcon Metals Limited

T: +61 8 6188 8181

ASX: FAL

E:info@falconmetals.com.au

Level 2, 22 Mount Street, Perth WA 6000

www.falconmetals.com.au

PO Box 7054 Cloisters Square WA 6850

ABN 87 651 893 097

1

Despite some initial delays, the start of aircore drilling at Ironbark East is also an exciting step for Falcon given the excellent results previously returned in the 2021 field season from the wide-spaced reconnaissance drilling program. With the progress of the work program to date at Karri, and now Ironbark, we are also delighted to enlarge the Pyramid Hill Gold Project with permit EL007200, which provides an opportunity to add further prospects to our portfolio."

Diamond Drilling Results at Karri

Diamond drilling has progressed at Karri with 7 holes now completed for 2,832m(Figure 1). Karri is a large 4km long gold anomaly defined by previous reconnaissance aircore drilling and 17 wide-spaced diamond holes. This previous drilling intersected several zones of mineralisation along interpreted upright anticlinal fold hinges like those known to host high-grade gold mineralisation across the Bendigo zone. Falcon's drilling in 2022 is targeting possible down-plunge and along strike extensions to these intercepts based on structural models from the region.

Assays for the first 4 holes have been received with the better results as below:

  • o PHKADD018 2m @ 3.32 g/t Au from 108m including 1m @ 6.51 g/t Au from 109m

  • o PHKADD020

  • o PHKADD021

including

1m @ 1.65 g/t Au from 190m 0.86m @ 1.26 g/t Au from 232.14m 1m @ 1.19 g/t Au from 232m 8m @ 1.08 g/t Au from 287m 1m @ 7.31 g/t Au from 294m 0.8m @ 1.15 g/t Au from 302.11m 1m @ 1.32 g/t Au from 308m 2m @ 2.01 g/t Au from 347m

Mineralisation in PHKADD018 was in the oxide zone and appears to be related to weathered sulphides in a sandstone with no quartz veining. It is in the western limb of an anticline, close to the hinge. This is in a similar position to the anomalous zone intersected previously in PHDH015 (5.1m @ 13.96 g/t Au from 100.9m, including 2.2m @ 32.10 g/t Au) that was also associated with iron oxides.

Mineralisation in PHKADD020 occurred in the west limb of the same anticline. It was associated with sericite alteration, disseminated pyrite and minor arsenopyrite.

The mineralised zones identified in PHKADD021 are of particular importance because they have extended the mineralisation in the eastern limb of this same anticline a further 100m to the north of mineralised structures intersected in PHDH007 (1m @ 5.40g/t Au from 192.8m) and PHDH015 (8m @ 1.05 g/t Au from 202m, including 1m @ 5.33 g/t Au). Mineralisation is associated with quartz veining, intermittent sericite alteration, and disseminated pyrite & arsenopyrite. In addition to the higher grades including 1m @ 7.31 g/t Au, broad zones of low-level Au mineralisation were also present within this zone including 16.2m @ 0.27 g/t Au from 299.8m and 27m @ 0.33 g/t Au from 341m(Figure2). Based on the encouraging results in PHKADD021, an additional hole, PHKADD025, has commenced. This is planned to test this mineralised target zone a further 100m north in the eastern limb of the mineralised anticline. At this preliminary stage this anticline, eastern fold limb and syncline are all considered prospective.

Figure 1 Plan map of Karri drilling

Figure 2 Schematic cross section of 5,985,450 N looking north showing the target zone covering the anticline, eastern limb and syncline

Aircore Drilling Commences at Ironbark East

Previous work at Ironbark has highlighted the association of gold mineralisation with the contact between Castlemaine Group Sediments and intrusive diorites, with some mineralisation hosted within the diorites. The successful reconnaissance aircore drilling program at Ironbark East during the 2021 field season significantly increased the priority of this prospect, especially given there are several analogous high-grade diorite-associated gold deposits in Eastern Victoria (Walhalla-Woods Point Goldfields) including Cohen's Reef (~1.5Moz @ 32 g/t Au)1.

The previous results at Ironbark East are considered by Falcon to be exceptional given they are on a wide-spaced reconnaissance line(Figure 3). Hole PA953 is particularly exciting given the intercept of

1 2006, Vandenberg et al., Walhalla-Woods Point-Tallangallook, Special map area geological report, Geoscience Victoria, Ch 8 -Economic Geology, page 231]

13m @ 1.52 g/t from 113m and ended in mineralisation. The next hole on this line, PA918, intersected 9m @ 0.91 g/t from 61m and is 200m west of PA953.

The aircore drilling at Ironbark East commenced in late March (Figure 4). This was later than planned due to the contracted drilling company having initial delays due to the impact from COVID-19, followed by equipment issues that are still preventing them from mobilising to site.

Falcon was able to contract a second drilling company that was in the process of commissioning an AC rig. Drilling rates have been slower than normal during the commissioning phase but as this is now completed, they are expected to improve throughout the rest of April. Drilling at Ironbark East will continue until cropping season commences in early May. Aircore drilling of other targets within the Pyramid Hill Project will be deferred until the commencement of the next drilling season in late Spring.

Figure 3 Map showing the proposed aircore drilling at Ironbark

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Falcon Metals Ltd. published this content on 12 April 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 12 April 2022 23:44:04 UTC.