Navigator Resources Ltd. announced production results for the month of August 2012 and for the three months June to August 2012 at Bronzewing Gold Project. For the month of June 2012, the company's BCMs was 628,930, ore mined of 246,230 t, ore grade of 1.28 g/t and total ounces mined of 10,114 oz.

Reconciled gold production (inclusive of gold in-circuit) for the reported three months June to August 2012 totalled 18,375 ounces.

As per the June 2012 quarterly report, the company can advise that reconciled gold production for the September 2012 quarter remains forecast to be in the range of 17,000 to 20,000 ounces.