Cadan Resources Corporation announced it has commenced the commissioning of the T'Boli plant. Having completed 4 months of rectification work on the plant at a total cost of CAD 670,000, while the newly built Tailings Dams completed will cost CAD 100,000. The dry testing of the plant commenced almost a week ago and was completed in 2 days.

The commissioning phase started on the 7th November and is expected to be completed by the end of December. As previously announced the plant will process the medium & low grade stockpiles whilst the re-development of the underground mine progresses toward accessing ore. The initial plan for processing medium to low grade mineralized material and tailings as required will provide feed for a minimum of 3 months.