Report of New Projects of Construction of Den Chai-ChiangRai-Chiang Khong

Railway, Contract 1, Den Chai-Ngao Section and Construction of Aerial-to-

underground Cable Project, the MRT Orange Line (East Section), Petchaburi Road

To:

The President

The Stock Exchange of Thailand

Right Tunnelling Public Company Limited (the "Company") is pleased to report a status of Construction of Den Chai-ChiangRai-Chiang Khong Railway, Contract 1, Den Chai-Ngao Section and a new construction project in August 2022 in total value of 556,500,000.00 Baht (including VAT) as follows:

1. Construction of Den Chai-ChiangRai-Chiang Khong Railway, Contract 1, Den Chai-Ngao Section

Project owner : The State Railway of Thailand

Employer : ITD-Nawarat Joint Venture

Project value : 2,281,256,591.42 Baht (including VAT)

Status of work : Entered into a contract on August 5, 2022

2. Construction of Aerial-to-underground Cable Project, the MRT Orange Line (East Section), Petchaburi Road

Project owner

:

Metropolitan Electricity Authority

Employer

:

Metropolitan Electricity Authority

Project value

:

556,500,000.00 Baht (including VAT)

Status of work :

Scheduled to sign a contract on August 11, 2022

It is therefore informed for your acknowledgement and dissemination to the investors and the public.

Sincerely yours,

(Mr. Chawalit Tanomtin)

Chief Executive Officer

The Office of Company Secretary

Tel: 02 313 4848 ext. 138 or 148

E-mail:cs@rtco.co.th

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Right Tunnelling pcl published this content on 09 August 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 09 August 2022 08:15:08 UTC.