Melior Resources Inc. updated the market about progress at its Goondicum Ilmenite Project. Commissioning and production ramp-up at Goondicum successfully continues to advance on schedule. Ilmenite production was 5,238 tonnes in January exceeding budget forecast. Production of secondary product apatite, of 317 tonnes was below forecast. Apatite sales represent around 15% of forecasted revenue and provides useful margin expansion. Modifications for the apatite circuit are being implemented and management is confident that apatite production will be brought up to budgeted levels over the next few months. Notable to highlight is that initiation of product offtake is on track. The first ilmenite shipment remains scheduled for First Quarter CY2019 and ilmenite haulage to the port from the mine has now commenced. No Lost Time Incidents were recorded during January and the project has been LTI free since the start of construction.