Pyrum Innovations AG continues to make good progress with its roll-out plan. The first works at the new Pyrum site in Perl-Besch started after the municipal council approved the development plan earlier this month. With the planned start of the clearing work, the site is now being prepared for further construction work.

At the end of last week, Pyrum received permission to clear the site, thus creating the basis for the construction area for the Pyrum plant and the new shredder. With a size of approximately 8,500 m2, this area is the first construction part of the planned new plant. Pyrum Innovations AG plans to build its second pyrolysis plant in Saarland in Perl-Besch by the end of 2025, based on the model of the main plant in Dillingen/Saar, with a capacity of 20,000 tonnes of end-of-life tyres (ELT) per year, which means doubling the current production capacity.

Construction is scheduled to start in the second half of 2024.