Infratek, with the business area Central Infrastructure, has been awarded a contract with the Finnish national power grid company Fingrid, for the turnkey delivery of a 110 kV substation.


The substation site is located close to the Helsinki capital area, approx. 35 km north of Infratek's Tammisto premises.

The value of the contract is approx. EUR 3.1 million and work will commence immediately.

The substation will be completed and handed over by the end of 2014. The turn-key delivery includes construction of new 110 kV gas insulated switchgear, protection and auxiliary systems and 110 kV underground cable connections to the national grid.

Infratek ASA

Oslo, 23 May 2013