SinoCoking Coal and Coke Chemical Industries, Inc. confirmed that its second aboveground facility for the production of syngas has been completed on schedule and will begin testing and calibration of systems on April 10. Located at the site of the company's first commercial syngas production facility in Pingdingshan, this second facility is expected to start deliveries to customers in May and reach full capacity of 25,000 cubic meters of syngas per hour by the end of June 2015. The company noted that these two facilities, with a combined output of 50,000 cubic meters per hour, would rank among China's large syngas aboveground production sites, in addition to being the only one that combines coking and producing syngas in parallel.

Additionally, they are among the first aboveground syngas facilities in China that can recycle carbon dioxide output to produce usable chemical compounds.