Cue Energy Resources Limited announced, planning continues for the First Quarter 2022 Palm Valley and Dingo exploration well drilling program. As a result of Buru Energy's ongoing operations, Ensign has advised that there will be
approximately a month delay to the Ensign 963 drilling rig's mobilisation to the Palm Valley field. The rig is now expected to mobilise to the Palm Valley well location in late February 2022, with commencement of the Palm Valley-12 well in March 2022. The Dingo-5 exploration well will be drilled back-to-back with Palm Valley-12.