Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 499 MWe
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 498 MWe
Unit 3 is in Mode 1 - stable operation on decreased power, Reactor power is 50 %, Turbine generator output - 247 MWe
Unit 4 is in Mode 1 - startup mode after refuelling, Reactor power is 65 %, Turbine generator output - 290 MWe

Electricity production since the beginning of the year: 14 141 833 MWh.

Jiří Bezděk , Spokesman of the ČEZ Group, Nuclear Power Plant Dukovany

Attachments

Disclaimer

CEZ a.s. published this content on 27 December 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 27 December 2023 06:28:35 UTC.