ASX ANNOUNCEMENT 3 FEBRUARY 2022
Black Rock Mining confirms 25% increase in Measured Mineral Resource,
now the largest in class globally
HIGHLIGHTS | ||
only | ||
∙ Completion of infill drill program and bulk metallurgical sampling has resulted in a 25% | ||
increase in Measured Mineral Resource | ||
∙ Mahenge now has the largest Measured graphite mineral resource globally | ||
∙ | Black Rock confirms the first 10 years of the Ulanzi mine plan (including all of Module 1 | |
and 2) is now underpinned by the highest confidence mineral resource category | ||
∙ | Mineral resource upgrade provides additional confidence for lenders and offtake | |
use | partners in the context of the debt financing process currently underway | |
Tanzanian graphite developer Black Rock Mining Limited (ASX:BKT) (Black Rock or the Company) is pleased
to announce that as a result of completing assays from the 2019 infill metallurgical drilling and bulk sampling program the JORC Compliant Mineral Resource Estimate and Ore Reserve, has been updated, posting a 25% increase in Measured Mineral Resource.
personalMahenge Graphite Mineral Resource Update
As part of the Company's ramp up on Project execution activities, Black Rock has completed an update of its Mahenge Mineral Resource designed to provide high confidence to customers and financiers on the planned production output over the first 10 years of operation from the Ulanzi open pit. The 25% increase in Measured Mineral Resource effectively confirms that 100% of the likely loan life is now underpinned by Measured Resource.
Drilling and bulk sampling was completed on the Ulanzi orebody in 2019 but held in storage for final customer qualification. This material was only recently assayed and used as an ore feed and processed in China and Canada as part of Black Rock's 500 tonne qualification processing plant campaign, refer ASX announcement 6th December 2021.
The complete report on the Mineral Resource Estimate is attached per Appendix 1. | |||||
Summary of the Mahenge Project JORC Mineral Resource update: | |||||
For | ∙ The global Mineral Resource Estimate for the Mahenge Graphite Project is 213.1M tonnes at 7.8% TGC | ||||
(Previously 211.9 Mt @ 7.8% TGC). This makes it the fourth largest JORC Mineral Resource globally and | |||||
it is still open along strike; | |||||
∙ Mineral Resource in the Measured category is now 31.8Mt and Indicated at 84.6Mt, combined | |||||
representing 55% of the total Mineral Resource; | |||||
∙ 25% increase in the measured Mineral Resource at Mahenge is the largest Measured Mineral Resource | |||||
of any graphite developer globally; | |||||
∙ Within this Mineral Resource is a higher grade portion of 43.8Mt @ 10.8% TGC; | |||||
Black Rock Mining Ltd | Australian Office | Tanzanian Office | Directors | ||
ACN 094 551 336 | Level 1, 1 Walker Ave | Mahenge Resources Ltd | Richard Crookes | Chairman | |
ASX: BKT | West Perth WA 6005 | Msasani Towers | John de Vries | Managing Director & CEO | |
Ph: +61 8 6383 6200 | Second floor Wing B | Gabriel Chiappini | Non-Executive Director/Company Secretary | ||
E: info@blackrockmining.com.au | Dar es Salaam | Ian Murray | Non-Executive Director | ||
Ph +255 767 907 920 |
www.blackrockmining.com.au
ASX ANNOUNCEMENT 3 FEBRUARY 2022
- Project de-risking achieved by:
Black Rock Mining Ltd | Australian Office | Tanzanian Office | Directors | |
ACN 094 551 336 | Level 1, 1 Walker Ave | Mahenge Resources Ltd | Richard Crookes | Chairman |
ASX: BKT | West Perth WA 6005 | Msasani Towers | John de Vries | Managing Director & CEO |
Ph: +61 8 6383 6200 | Second floor Wing B | Gabriel Chiappini | Non-Executive Director/Company Secretary | |
E: info@blackrockmining.com.au | Dar es Salaam | Ian Murray | Non-Executive Director | |
Ph +255 767 907 920 |
www.blackrockmining.com.au
ASX ANNOUNCEMENT 3 FEBRUARY 2022
About Black Rock
Black Rock Mining Limited is an Australian based company listed on the Australian Securities Exchange (ASX:BKT). The Company has a 100% interest in the Mahenge Graphite Project (Project) located in Tanzania. The Project has a JORC compliant Mineral Resource Estimate of 213m tonnes at 7.8% TGC. It also has Ore Reserves of 70.5m tonnes at 8.5% onlyTGC. The Ore Reserves support a mine life of up to 340k tonnes of graphite per annum for a reserve life of 16 years. Since the release of the Mineral Resource Estimate, the Company confirms that it is not aware of any new information
or data that materially affects the mineral resources estimate.
On 25 July 2019, the Company released an enhanced Definitive Feasibility Study (eDFS) for the Project. The eDFS for the Mahenge Graphite Mine envisages a four phase operation, ultimately producing 340,000 tpa of high-grade graphite, with exceptional financial metrics including:
- Low Capex: Lowest peak capital expenditure of US$116M for phase one*;
- High Margin: AISC margin of 63.1%;
- Low Technical Risk: Substantial pilot plant operations run of 110 tonnes; and
- Superior Economics: IRR of 44.8% with NPV10 of US$1.16bn (A$1.65bn**)
useBlack Rock has obtained all Environmental approvals, Mining Licences and its Resettlement Action Plan with clear title to the eDFS project area. An FCI Agreement was signed with the Government of Tanzania in December 2021.
In June 2020, the Company announced a Strategic Alliance with POSCO Group for the development of the Mahenge Graphite Mine. This included an equity investment of US$7.5M, signed in February 2021. In December 2021, a Term Sheet was agreed with POSCO for a US$10M prepay and life of mine fines offtake for Module 1. Black Rock has also llocated planned production through Pricing Framework Agreements (ASX release 8 May 2019) with five other offtake customers.
Following release of the enhanced DFS (eDFS) in July 2019, the Company confirms that it is not aware of any new data or information that materially affects the results of the eDFS and that all material assumptions and, in the case of estimates of Mineral Resources or Ore Reserves, technical parameters underpinning the estimates in the relevant market announcements continue to apply and have not materially changed.
The estimated Ore Reserves and Mineral Resources underpinning the production target has been prepared by competent persons in accordance with the requirements in Appendix 5A (JORC Code).
The Company is construction-ready subject to financing.
personal | JORC Compliant Mineral Resource Estimate and Ore Reserve*** | |||||
Ore Reserves | Tonnes (Mt) | Grade (% TGC) | Contained Graphite (Mt) | |||
- Proven | - | - | - | |||
For | - Probable | 70.5 | 8.5 | 6.0 | ||
Total Ore Reserves | 70.5 | 8.5 | 6.0 | |||
Mineral Resources | ||||||
- Measured | 31.8 | 8.6 | 2.7 | |||
- Indicated | 84.6 | 7.8 | 6.6 | |||
Total M&I | 116.4 | 8.0 | 9.3 | |||
- Inferred | 96.7 | 7.4 | 7.2 | |||
Total M, I&I | 213.1 | 7.8 | 16.6 | Location of Black Rock's Mahenge Graphite Project in Tanzania |
For further information on Black Rock Mining Ltd, please visit www.blackrockmining.com.au
- Forecast Capex has been classified as a Class 3 estimate with accuracy of ±10% as defined by AACE ** AU$/US$ 0.70
*** Resource and Ore Reserve Estimates as released to ASX on 3 February 2022.
Black Rock Mining Ltd | Australian Office | Tanzanian Office | Directors | |
ACN 094 551 336 | Level 1, 1 Walker Ave | Mahenge Resources Ltd | Richard Crookes | Chairman |
ASX: BKT | West Perth WA 6005 | Msasani Towers | John de Vries | Managing Director & CEO |
Ph: +61 8 6383 6200 | Second floor Wing B | Gabriel Chiappini | Non-Executive Director/Company Secretary | |
E: info@blackrockmining.com.au | Dar es Salaam | Ian Murray | Non-Executive Director | |
Ph +255 767 907 920 |
www.blackrockmining.com.au
ASX ANNOUNCEMENT 3 FEBRUARY 2022
The Mahenge Project JORC Mineral Resource
The Mineral Resource Estimate was completed by Trepanier Pty Ltd, an independent geological consultancy. The summary tables below display the Measured, Indicated and Inferred Mineral Resources for the combined Mahenge Project and individually by each prospect.
For personal use only
Table 1. Mahenge Global Mineral Resource summary table
Category | Tonnes | TGC | Contained TGC | ||
(Millions) | (%) | (Million tonnes) | |||
Measured | 31.8 | 8.6 | 2.7 | ||
Indicated | 84.6 | 7.8 | 6.6 | ||
Inferred | 96.7 | 7.4 | 7.2 | ||
TOTAL | 213.1 | 7.8 | 16.6 | ||
Table 2. Mahenge Mineral Resource breakdown by prospect
Tonnes | TGC | Contained TGC | ||
Prospect | Category | (Millions) | (%) | (Million tonnes) |
Ulanzi | Measured | 19.6 | 8.8 | 1.7 |
Indicated | 46.2 | 8.2 | 3.8 | |
Inferred | 48.7 | 7.8 | 3.8 | |
Sub-total | 114.5 | 8.1 | 9.3 | |
Cascades | Measured | 12.1 | 8.3 | 1.0 |
Indicated | 20.8 | 8.3 | 1.7 | |
Inferred | 27.3 | 7.9 | 2.2 | |
Sub-total | 60.2 | 8.1 | 4.9 | |
Epanko | Measured | |||
Indicated | 17.6 | 6.4 | 1.1 | |
Inferred | 20.8 | 5.9 | 1.2 | |
Sub-total | 38.4 | 6.1 | 2.4 | |
COMBINED | MEASURED | 31.8 | 8.6 | 2.7 |
INDICATED | 84.6 | 7.8 | 6.6 | |
INFERRED | 96.7 | 7.4 | 7.2 | |
TOTAL | 213.1 | 7.8 | 16.6 | |
Note: Appropriate rounding applied
BLACKROCKMINING.COM.AU
ASX ANNOUNCEMENT 3 FEBRUARY 2022
Mahenge Project global Mineral Resource Estimate breakdown by cut-off grades
Table 3 and Figure 1 below show the Mahenge global resource at varying cut-off grades and the corresponding grade-tonnage curve, respectively. Of note is that a significant high-grade resource is contained within the global 213.1Mt @ 7.8% TGC resource. At a 9% cut-off, a high-grade portion of 43.8Mt
- 10.8% TGC is available or at a 10% cut-off, a 24.9Mt portion of the Mineral Resource Estimate exists at 11.8% TGC.
Table 3. Mahenge Global Mineral Resource by grade cut-off
only | Cut-off TGC | Million tonnes | TGC (%) |
0 | 213.1 | 7.8 | |
1 | 213.1 | 7.8 | |
use | 2 | 213.0 | 7.8 |
3 | 212.7 | 7.8 | |
4 | 211.4 | 7.8 | |
5 | 202.9 | 7.9 | |
6 | 176.1 | 8.3 | |
7 | 133.5 | 8.9 | |
8 | 84.3 | 9.7 | |
9 | 43.8 | 10.8 | |
10 | 24.9 | 11.8 | |
11 | 14.3 | 12.8 | |
12 | 7.8 | 13.9 | |
personalFor | 13 | 5.2 | 14.6 |
Graph Graph 1. Global Mahenge TGC% grade-tonnage curve | |||
BLACKROCKMINING.COM.AU
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Black Rock Mining Ltd. published this content on 02 February 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 02 February 2022 22:38:04 UTC.