The fire occurred in a part of one production building on the site in
Although our impact assessment of the damage is ongoing, our current view is the following:
Our Metrology and Inspection output plans are not affected as they do not contain any components made in
The manufacturing of DUV components has been restarted. Although there was some disruption regarding components for DUV, we expect to remediate this in such a way that it will not affect our output and revenue plan for DUV
As to EUV, the fire affected part of the production area of the wafer clamp, a module in our EUV systems. We are still in the process of completing the recovery plan for this production area and determining how to minimize any potential impact for our EUV customers, both in our output plan and in our field service.