Altyn Plc announced the expansion of the Tailing Storage Facility at Sekisovskoye Gold Processing Plant. The design of the construction of section IV of tailing storage facility (TSF) at Sekisovskoye gold processing plant is nearing completion as of October 2020. The construction work is planned to start in Second Quarter 2021 as soon as the required permits and approvals from state supervision authorities are obtained. As such, an additional storage facility will be built for stowing over 1.0 million m3 of tailing solids, which should allow uninterruptible operation of the gold processing plant until 2024. Furthermore, preliminary design work on the construction of section V of TSF has commenced. It is expected that this will be commissioned in 2023 which will ensure the continuity in operation of the gold processing plant after 2024.