1

CONTENTS

INTRODUCTION ....................................................................................................................................

3

SUMMARY OF IPO FUNDS GENERATED.....................................................................................

3

IMPLEMENTATION STATUS.............................................................................................................

4

1.

UTILIZATION OF IPO PROCEEDS ON LOCAL COST COMPONENTS....................

4

2.

SHIPMENT AND INSTALLATION OF MI DA ROLLING MILL ......................................

4

3.

SHIPMENT AND INSTALLATION OF AIR SUPRESSION UNIT ..................................

5

4.

PRE COMMISSIONING AND COMMISSIONING..............................................................

5

ANNEXURE - I ........................................................................................................................................

6

ANNEXURE - II.......................................................................................................................................

8

2

PROGRESS REPORT

INTRODUCTION

This Progress report is being submitted as per Regulation 16 of the Public Offering Regulations, 2017

  • in compliance with the requirement specified in clause 4.1.10 of the prospectus to the issue of the Company.

AGHA STEEL INDUSTRIES LIMITED carried out a successful IPO in October 2020 to finance its expansion at estimated cost as detailed below:

Break up of IPO Proceeds Utilization

Rupees

Civil Works

377,380,707

Electrical

486,387,463

Mechanical

458,231,960

Duties and Others

534,403,866

Air Separation Unit

399,735,446

LC Discount Charges

193,860,558

Contingency

150,000,000

Working Capital Requirement

1,000,000,000

In this respect, We would like to update the following progress has been achieved on the implementation of the phase II during the period ended Nov 02, 2022 after listing on PSX and in accordance with financial results uploaded at PSX in respect of aforementioned projects in the ensuing pages.

SUMMARY OF IPO FUNDS GENERATED

Description

Rupees

Issuance of 120 million ordinary shares at floor price of Rs. 30 per share

3,600,000,000

Excess funds received - Share Premium at Rs. 2 per share

240,000,000

Less: Share issuance costs

(225,275,000)

Net IPO Proceeds

3,614,725,000

3

PROGRESS REPORT

IMPLEMENTATION STATUS

1. UTILIZATION OF IPO PROCEEDS ON LOCAL COST COMPONENTS:

Break up of IPO Proceeds

Completed

Cost to be

Already utilized

Percentage of

Utilization

incurred

Completion

Civil Works

Completed

377,380,707

1,073,825,000

100%

Electrical

Completed

486,387,463

452,023,000

90%

Mechanical

Completed

458,231,960

665,277,000

90%

Duties and Others

Completed

534,403,866

535,410,000

90%

Air Separation Unit

Completed

399,735,446

694,329,000

100%

LC Discount Charges

Completed

193,860,558

193,860,558

100%

Contingency

Completed

150,000,000

-

N/A

Working Capital Requirement

Completed

1,000,000,000

-

N/A

3,600,000,000 3,614,725,000

2. SHIPMENT AND INSTALLATION OF MI DA ROLLING MILL:

S.no

Commitment made in

Start

date

Completion

Current

Rational for Delay, If

prospectus

(disclosed in

date (disclosed

Status

any

prospectus)

in prospectus)

1

Shipment of the Mi.Da

January 2020

March 2020

Completed

N/A

rolling mill

2

Installation of the of

Foreign Travel

Mi.Da rolling mill.

September

restrictions on

December 2020

In Progress

account of COVID-19

2020

pandemic/ other

economic issues

Please refer 'Annexure - I' for pictorial representation of the under process Civil, Electrical and Mechanical works involved in implementation of MI DA rolling mill would give an idea over pace of progress

4

PROGRESS REPORT

3. SHIPMENT AND INSTALLATION OF AIR SUPRESSION UNIT:

S.no

Commitment made

Start

date

Completion

Current

Rational for Delay, If any

in prospectus

(disclosed in

date

Status

prospectus)

(disclosed in

prospectus)

1

Shipment of Air

August 2020

October 2020

Completed

N/A

Separation Unit

2

Installation of Air

November

December

Completed

N/A

Separation Unit

2020

2020

Please refer 'Annexure - II' for pictorial representation of the under process Civil, Electrical and Mechanical works involved in implementation of Air Separation Unit would give an idea over pace of progress.

4. PRE-COMMISSIONING AND COMMISSIONING:

S.no

Commitment made

Start

date

Completion

Current

Rational for Delay, If any

in prospectus

(disclosed in

date

Status

prospectus)

(disclosed in

prospectus)

Foreign Travel

1

Pre-Commissioning

January 2021

March 2021

In progress

restrictions on account of

and Commissioning

COVID-19 pandemic /

other economic issues

___________________

____________________

Company Secretary

Chief Financial Officer

5

This is an excerpt of the original content. To continue reading it, access the original document here.