Tyranna Resources Ltd. announced drilling has commenced at the Muvero Prospect, the first drill-target to be tested. A summary of the drilling program is: Diamond drilling (HQ and NQ), 6 drill-holes planned with total planned meters = 1,100m, Commenced 17 October 2022, estimated completion; end of November 2022, Anticipated receipt of results; late December 2022 to February 2023. Drilling has been planned that provides critical information that will enable optimised follow- up drilling and for these initial results to be able to be incorporated in a subsequent resource drill-out if this occurs.NDDH001 was collared at 221587mE/8322755mN (WGS-84 z33L); location from handheld Garmin GPSMap 64, accuracy +/- 3m.

This location is about 10m north of the initially planned location and at the time of writing, the drill- hole was passing through fractured partly weathered coarse-grained mafic host-rock, consistent with the exposed bedrock at this location.