Sotkamo Silver AB announced production results for the first two months of 2020. During the first two months of 2020 ca. 82 kt of ore was processed at the Silver Mine. This yielded ca. 264 000 ounces of silver, 353 tons of lead, 741 tons of zinc and 634 ounces of gold in the concentrates.

The company provided production guidance for 2020. For the year, the company expects to process 480 kt to 540 kt of ore in 2020 whereas in 2019 Silver Mine processed 343 kt of ore. Correspondingly, the silver production in 2020 is forecasted to be 1.4 million ounces to 1.7 million ounces.