Robex Resources Inc. provided production guidance for the third quarter of 2013. The company announced that following the funding of $4 million, its production target set out after commissioning of its plant are increased by 53%. The company announced that, in recent months, the company's' team and an engineering firm have worked extensively on optimizing the process of the plant.

The flow sheet of the process was optimized and redefined. In addition, the equipment has been sized accordingly by the engineering firm. Furthermore, multiple tests have confirmed that a cyanidation time of 16 hours was adequate to maintain the recovery rate at 88% - 90%.

As a result, the production target set for the commissioning of its plant in the third quarter of 2013 is now 2,300 tones per day (t /d), compared to the objectives of 1,500 t /d initially planned. During the year following the start of the plant, the company expects to achieve 6,000 t /d by the gradual addition of cyanidation tanks. The construction and planned expansions will be realized in three phases: Phase 1, the current phase of start-up includes the feed system, the cyanidation circuit (CIL) and the gold recovery system.

Phase 2 includes the crushing and grinding circuit and phase 3 of a second feed circuit. Each phase includes sub-phases. These sub-phases correspond to the gradual addition of cyanide tanks.

The exploration of the Mininko property will continue meanwhile with the objective of increasing the resource to such level that it could possibly increase future level of production at Nampala beyond the 6,000 tones per day planned. In the event of a significant increase in resources, the second and third phases of expansion could proceed eventually.