London, 3 January 2012: Ophir announces the start of its 2012
drilling programme in Tanzania with the drillship Odfjell
Metro-1. The first three wells in the programme will be
Jodari-1, Mzia-1 (previously named 1W) and Papa-1 (previously
named 3A).
The Metro-1 is a state-of-the-art drillship capable of
drilling in water depths of up to 3,000m. The rig has a dual
derrick with a main work centre and an auxiliary work centre
to facilitate a number of simultaneous operations. Both work
centres are equipped for drilling. The Metro-1 was built at
the Hyundai Heavy Industries yard in Ulsan, South Korea and a
detailed series of acceptance tests have been performed ahead
of mobilisation to Tanzania.
The Jodari-1 and Mzia-1 wells are both located in Block 1.
For efficiency reasons the Mzia-1 top hole section will be
drilled first, as part of a batch drilling programme, then
the rig will move to drill Jodari-1 in its entirety, before
returning to Mzia-1 to complete the bottom portion of the
well.
The Mzia-1 well spudded in 1,500m of water on 1 January 2012
and drilling of the top hole section is expected to take 7 to
10 days. Thereafter the Jodari-1 well will spud in a water
depth of 1,155m and drill to total depth of c 4,600m subsea
in an estimated 40 days. The Jodari prospect contains
multiple stacked targets in both the Tertiary and Cretaceous
sections with the former having seismic flat spot and
amplitude fit to structure. Jodari is modelled by Ophir to
contain mean resources of 2.2Tcf in the stacked targets.
Ophir holds 40% of Blocks 1, 3 and 4 and has now fully handed
over operatorship to 60% partner BG International, who will
manage the programme with the Metro-1.
The Fugro Geo Caribbean seismic vessel commenced mobilisation in the East Pande licence on 30 December 2011. The 2,200km2 3D seismic programme is expected to take 40 days to complete and is designed to mature prospects for possible drilling late in 2012. Ophir holds 70% of the East Pande licence and operates the Block.
Equatorial Guinea Rig Contract
Ophir expects imminently to conclude negotiations to secure a
rig for a 3 to 4 well drilling programme in the extended
Block R, Equatorial Guinea. The programme, which is designed
to demonstrate sufficient gas volumes to underpin a planned
second LNG train in Equatorial Guinea, will include one or
more appraisal wells on Ophir's earlier Fortuna-1 discovery,
plus exploration wells on the Tonel and Silenus
prospects.
Due to rig availability, this programme is now expected to
start in late March. It is anticipated that the programme
will take approximately 60 days. Ophir holds 80% of the Block
R licence and operates the Block.
The PGS Apollo seismic vessel commenced mobilisation from
Port Gentil on 26 December 2011. The 2,100km2 3D
seismic programme is expected to take 42 days to complete.
The survey is specifically designed to mature pre-salt
targets for drilling in late 2012. Ophir holds 50% of the
Mbeli and Ntsina licences and operates them; Petrobras holds
the remaining 50% of the blocks.
Ophir CEO, Nick Cooper said: "2012 has the potential to be
transformational for Ophir. We are pleased to start the year
by kicking off our Tanzanian drilling programme and also to
see drilling and seismic operations gearing up across our
other key assets. Ophir plans to drill at least 9 wells
across our portfolio in 2012."
Ophir Energy plc +44 (0)20 7290 5800
Nick Cooper, CEO
FTI Consulting (PR Advisor to Ophir) +44 (0)20 7269 7157
Billy Clegg/Edward Westropp
distribué par | Ce noodl a été diffusé par Ophir Energy plc et initialement mise en ligne sur le site http://www.ophir-energy.com. La version originale est disponible ici. Ce noodl a été distribué par noodls dans son format d'origine et sans modification sur 2012-01-03 17:37:44 PM et restera accessible depuis ce lien permanent. Cette annonce est protégée par les règles du droit d'auteur et toute autre loi applicable, et son propriétaire est seul responsable de sa véracité et de son originalité. |
Documents associés | |
Drilling & Operational Update |