Melbana Energy Limited reports that drilling operations at its Alameda-1 exploration well in its Block 9 contract area onshore Cuba have been continuous over the Christmas/New year period. Upon reaching a depth of 2,500 mMD the drilling plan called for the installation of the 10kpsi BOP,
consistent with conservative industry recommended practice. Given the stable conditions experienced down hole to that point, it was decided to review the ongoing activities as there was a risk that they could not be completed consistent with best practice for well control. With the agreement of the drilling contractor, the drilling plan was amended to drill ahead and set the 9-5/8" casing string at approx. 2,700 mMD before swapping to the 10kpsi BOP to continue to maintain best practice standards as progress to well TD. A short while ago the well had reached 2,511 mMD.