Integrated Green Energy Solutions Ltd. provided the following update regarding the construction of its Amsterdam facility. Onsite construction at the Amsterdam project continues to progress. All piling was completed in early October. IGES's builder, Ijbouw B.V., has now informed IGES that all form work for the foundation concrete beams is also now complete, with pouring into the trenches to be finalised by the end of the week. Once the reinforced trenches are filled with concrete, this will provide support for the fuel production and plastic processing buildings. Final excavation work around pile tops is then completed and the slab will be poured, allowing the fuel production and plastic processing buildings to be erected. The concrete slab pour is on schedule to be completed in November. The pouring of the concrete slab will also allow the tank farm and the gas storage area to be constructed.