With reference to the current report No. 5/2013 of 4 March 2013 and No. 44/2016, the Management Board of ELEKTROBUDOWA SA ("the Company") informs that an amendment ("the Amendment") to the contract for "Extension and modernization of Byczyna station including connection of the 400 kV line", being performed under the contract made with Polskie Sieci Elektroenergetyczne SA having its registered office in Konstancin - Jeziorna, has been signed today.

By the Amendment the Parties have agreed the changes to the contract Schedule concerning the dates for completion of the project stages. Following the changes, the deadline for completion of the whole project is now 31 December 2018.

The Amendment does not change the scope of the contract or the contract price.

Legal basis
Art. 17.1 MAR -inside information

The Company's authorized representatives:
Janusz Juszczyk, President
Paweł Skrzypczak, Vice President

Elektrobudowa SA published this content on 17 March 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 28 March 2017 10:00:12 UTC.

Public permalinkhttp://www.publicnow.com/view/499D037EFF38F072734AAF4F9D20AB1AC9F1C148