The board of directors of Diamond Building Products Public Company Limited at the Meeting No. 381, dated December 18, 2023, unanimously approved the investment project for installation of autoclaved aerated concrete production machinery (AAC-2), having a production capacity of approximately 2,880,000 square meters or approximately 163, 200 tons per year, with an investment of approximately THB 648 million. The procurement and installation of the machinery is anticipated to take approximately 14 months, with production of autoclaved aerated concrete products expected to commence by the second quarter 2025.

The investment project for installation of autoclaved aerated concrete production machinery is currently in the process of preparing the terms of reference (TOR) and selecting machinery suppliers. Upon its completion, the company will later provide relevant information.