Conifex Timber Inc. announced that it has made the difficult decision to take unscheduled downtime for four weeks at its Mackenzie, British Columbia sawmill commencing June 5, 2023. It is anticipated that the unscheduled downtime will impact production capacity by approximately 16 million board feet. The downtime is necessitated by the low water levels forecasted in the Williston Reservoir negatively impacting Conifex's ability to safely and efficiently utilize its reservoir assets and reduced demand for lumber products amid challenging economic conditions.

Conifex intends to utilize the production downtime to complete critical maintenance activities at its sawmill. Conifex expects to resume normal lumber production operations in July 2023, but will closely monitor market conditions and adjust production plans accordingly. Conifex's power plant operation will remain unaffected.