For personal use only

ASX and MEDIA RELEASE

24 January 2022

Quarterly Activities Report to 31 December 2021

Tomingley Gold Operations (Tomingley)

  • Gold production met forecast for the quarter of 16,935oz, with site operating cash costs at A$1,089/oz and AISC of A$1,338/oz.
  • Gold sales of 17,754 ounces for revenue of A$43.9M at an average price of A$2,475/oz.
  • FY2022 production guidance for Tomingley is unchanged at 55,000oz to 60,000oz. FY2022 AISC guidance has lifted to $A1,500/oz to $1,650/oz due to the potential cost impact of the combined effects of workers self-isolating during the current omicron wave and from heavy rainfall impacting the pit walls and access ramp.

Tomingley Gold Extension Project (TGEP)

  • The Environmental Impact Statement has been finalised and submitted to the NSW Government for their final review. Formal submission is expected later this month. The expected timing of Project Approval remains mid-2022.

Exploration

  • The drill program at Boda continues to show extensive mineralisation, including high grade zones, over a 3km strike length from Boda Three to Kaiser. (see ASX Announcements 22 October 2021 and 17 December 2021)
  • At Boda significant results included:

BOD059

906.7m grading 0.45g/t Au, 0.18% Cu from 309m

incl

219m grading 0.28g/t Au from 309m (gold only flanking zone)

also

672.7m grading 0.51g/t Au, 0.23% Cu from 543m

incl

115m grading 1.98g/t Au, 0.53% Cu from 864m

incl

2.8m grading 13.0g/t Au, 1.59% Cu from 901.5m

also

33m grading 4.06g/t Au, 1.29% Cu from 946m

incl

6m grading 11.2g/t Au, 1.81% Cu from 968m

KSDD043

927m grading 0.31g/t Au, 0.16% Cu from 159m

incl

157m grading 0.31g/t Au from 159m (gold only flanking zone)

also

754m grading 0.31g/t Au, 0.19% Cu from 332m

incl

74.7m grading 0.92g/t Au, 0.36% Cu from 680m

incl

12m grading 3.01g/t Au, 0.65% Cu from 732m

also

38m grading 0.60g/t Au, 0.79% Cu from 875m

incl

9m grading 1.04g/t Au, 1.40% Cu from 839m

also

6m grading 1.26g/t Au, 0.12% Cu from 1080m

CONTACT

: NIC EARNER, MANAGING DIRECTOR, ALKANE RESOURCES LTD, TEL +61 8 9227 5677

INVESTORS

:

NATALIE CHAPMAN, CORPORATE COMMUNICATIONS MANAGER, TEL +61 418 642 556

MEDIA

:

PAUL RYAN, CITADEL-MAGNUS, TEL +61 409 296 511

Level 4, 66 Kings Park Rd, West Perth WA 6005, AUSTRALIA (PO Box 768, West Perth WA 6872, AUSTRALIA)

Telephone: +61 8 9227 5677 Facsimile: +61 8 9227 8178 www.alkane.com.au mail@alkane.com.au

For personal use only

  • The preparation of an initial resource estimation for Boda continues, expected at the end of the current quarter.

Corporate

  • Cash, bullion and listed investments position totalled A$118.3M.
  • The debt facility of $20M with Macquarie Bank was repaid during the quarter.
  • Shareholding of ASX listed gold developer Calidus Resources Ltd (ASX:CAI) was ~9.7% at end of December quarter.
  • Shareholding of ASX listed gold developer Genesis Minerals Ltd (ASX:GMD) was ~12.7% at end of December quarter. During the quarter GMD shares to the value of $18.9M were sold.

2/11

Alkane Resources Ltd - 31 December 2021 Quarterly Report 24 January 2022

For personal use only

TOMINGLEY GOLD OPERATIONS

Tomingley Gold Operations Pty Ltd 100%

Tomingley Gold Operations (Tomingley) is a wholly owned subsidiary of Alkane, located near the village of Tomingley, approximately 50km southwest of Dubbo in Central Western New South Wales. The gold processing plant was commissioned in January 2014 and has been operating at the design capacity of 1Mtpa since late May 2014. Mining is based on four gold deposits (Wyoming One, Wyoming Three, Caloma One and Caloma Two).

Operations Performance

Tomingley underground continued to perform well during the quarter. The cutback in the northeast of the Caloma pit also performed well. The omicron COVID-19 outbreak in NSW has resulted in a number of employees and their close contacts testing positive, requiring isolation and recovery. At times this has affected approximately 10 to 20% of the workforce. In addition, very high rainfall has occurred in western NSW, resulting in some pit wall and ramp erosion that required remediation and stabilisation.

Despite these circumstances FY2022 production guidance for Tomingley is unchanged at 55,000oz to 60,000oz. FY2022 AISC guidance has however been lifted to $A1,500/oz to $1,650/oz due to the expectation of potential cost increase, due to productivity impacts.

A total of 16,935 ounces of gold was poured for the quarter. The site cash costs for the quarter were A$1,089/oz with an all-in sustaining cost (AISC) of A$1,338/oz.

Gold sold for the quarter was 17,754 ounces at an average sales price of A$2,475/oz, generating revenue of A$43.9M. Bullion stocks were 1,203 ounces (fair value of A$3.0M at quarter end). Site operating cash flow was A$25.7M for the quarter.

Tomingley Gold Extension Project

Alkane's intention is to develop the Roswell and San Antonio deposits, which are located 3 - 5km south of Tomingley, as soon as possible.

Alkane continues to progress approvals for this development. The Environmental Impact Statement has been finalised and submitted to the NSW Government for final review. Formal submission is expected later in January 2022. The expected timing of Project Approval remains mid-2022.

3/11

Alkane Resources Ltd - 31 December 2021 Quarterly Report 24 January 2022

For personal use only

Regional Exploration

Near-mine exploration continued at Tomingley targeting additional mineralisation outside the existing resource models at Roswell and San Antonio, as well as Macleans, El Paso and the Plains prospect to the east of Roswell.

Tomingley FY 2022 Quarterly and Annual Production Figures

Tomingley Production

FY

Sep Quarter

Dec Quarter

FY

2021

2021

2021

2022

Open cut

Waste mined

BCM

1,218,779

290,371

233,937

524,308

Ore mined

Tonnes

71,347

93,118

91,185

184,303

Strip Ratio

Ratio

32.8

8.0

7.2

8.0

Grade

g/t

0.64

0.63

0.83

0.73

Underground

Ore mined

Tonnes

706,889

226,054

208,534

434,588

Grade

g/t

2.63

1.87

2.42

2.29

Ore milled

Tonnes

928,531

247,884

257,384

505,268

Head grade

g/t

2.14

1.79

2.42

2.11

Recovery

%

88.8

85.1

85.4

85.2

Gold poured

Ounces

56,958

12,141

16,935

29,076

Revenue Summary

Gold sold

Ounces

55,929

13,359

17,754

31,113

Average price realised

A$/oz

2,286

2,467

2,475

2,472

Gold revenue

A$M

127.8

33.0

43.9

76.9

Cost Summary

Surface works

A$/oz

17

263

199

227

Mining

A$/oz

452

709

431

550

Processing

A$/oz

347

406

321

357

Site Support

A$/oz

125

154

138

145

C1 Site Cash Cost

A$/oz

940

1,531

1,089

1,279

Royalties

A$/oz

73

65

78

73

Sustaining capital

A$/oz

296

268

114

180

Gold in circuit movement

A$/oz

-58

16

-6

3

Rehabilitation

A$/oz

20

20

20

20

Corporate

A$/oz

49

61

42

50

AISC1

A$/oz

1,320

1,961

1,338

1,606

Bullion on hand

Ounces

3,246

2,025

1,203

1,203

Stockpiles

Ore for immediate milling

Tonnes

71,938

143,535

185,869

185,869

Grade

g/t

0.95

0.92

0.85

0.85

Contained gold

Ounces

2,856

4,246

5,114

5,114

1AISC = All in Sustaining Cost comprises all site operating costs, royalties, mine exploration, sustaining capex, mine development and an allocation of corporate costs, calculated on the basis of ounces sold. AISC does not include share based payments or net realisable value provision for ore inventory.

4/11

Alkane Resources Ltd - 31 December 2021 Quarterly Report 24 January 2022

For personal use only

5/11

Alkane Resources Ltd - 31 December 2021 Quarterly Report 24 January 2022

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Alkane Resources Limited published this content on 23 January 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 23 January 2022 21:23:02 UTC.