ASX RELEASE
20 APRIL 2022
DRILLING COMMENCES AT MULGA TANK
HIGHLIGHTS
• Diamond drilling program at the Mulga Tank Ni-Cu-PGE Project has now commenced
• Program expanded to 10 holes after further targeting work at NW3 Conductor
• Four additional bedrock conductors identified in the Panhandle NW Sector
• Successful completion of due diligence on sale of Pavarotti Project iron ore rights - cash payment of $200,000 expected to be received this week
• Proceeds of sale will allow further expansion of Mulga Tank drilling program
• Company is entering an exciting period of ongoing nickel exploration news flow at the flagship Mulga Tank Ni-Cu-PGE Project
Western Mines Group Ltd (WMG or Company) (ASX:WMG) is pleased to update shareholders on the commencement of the Company's maiden diamond drilling program at the flagship Mulga Tank Ni-Cu-PGE Project, on the Minigwal Greenstone Belt, in Western Australia's Eastern Goldfields. Numerous exciting drill targets have been defined at the project (ASX, Mulga Tank Ni-Cu-PGE Project: Major Targets Drill Ready, 6 April 2022) that will be tested with an expanded ten-hole diamond drilling program totalling 4,050m; following additional targeting work at the NW3 Conductor. Additional follow-up holes will be planned based on initial pXRF and Downhole Electromagnetic (DHEM) results as the program progresses.
WMG's systematic exploration approach combining geophysical, geological and geochemical vectoring work continues to build a robust exploration model for the discovery of nickel sulphide mineralisation within this large and highly prospective ultramafic intrusion.
Commenting on the Mulga Tank Project, WMG Managing Director Caedmon Marriott said:
"Drilling has now commenced at Mulga Tank and WMG has entered into what will hopefully be an exciting three to four month period for the Company. Each hole will take between eight to fifteen days to complete, depending on depth, and we will update shareholders on significant news flow as the program progresses. The Company is also pleased to have completed the due diligence hurdle for the sale of the Pavarotti Project iron ore rights to Mineral Resources. Cash proceeds of $200,000 are expected to be received this week and these funds will go towards expanding the Mulga Tank drilling program."
Shares on Issue: 44.65m | ||
Share Price: $0.29 | ||
Level 3, 33 Ord Street | Telephone: +61 475 116 798 | Market Cap: $12.95m |
West Perth WA 6005 | Email:contact@westernmines.com.au | Cash: $4.54m (30/12/21) |
ASX:WMG | www.westernmines.com.au |
Western Mines Group Ltd
MULGA TANK DIAMOND DRILLING PROGRAM
WMG designed an initial nine-hole diamond drilling program, totalling 3,750m, to test numerous drill targets identified from the Company's recently completed high-powered Moving Loop Electromagnetic (MLEM) survey (ASX, Major EM Targets Identified at Mulga Tank Ni-Cu-PGE Project, 7 March 2022; Mulga Tank Ni-Cu-PGE Project: Major Targets Drill Ready, 6 April 2022). This drilling program has now been expanded to ten holes, totalling 4,050m, after the completion of additional targeting work around the NW3 Conductor bedrock anomaly in the NW Sector or "Panhandle" area of the Mulga Tank intrusion.
Figure 1: Mulga Tank MLEM mid-late channel CH35BZ image showing EM plates and WMG's planned drill holes
Drilling commenced at the project this morning, starting at planned hole MTP012. The program is anticipated to take around three months to complete with each hole taking between eight and fifteen days, depending on depth. The Company intends to update shareholders on significant news flow as the program progresses.
The targets and drill holes selected are based on a combination of geophysical modelling of the recent MLEM results along with geological interpretation of the intrusion and geochemical vectoring work. Follow-up holes will be planned based on the interpretation of initial pXRF and DHEM results, which would see this initial program expand.
HoleID | Target | Description |
MTP012 | Geology | Testing western margin of the intrusion between holes MTD003, MTD005 and the W Conductor |
MTP013 | EM | Testing basal contact of western margin at top of W Conductor |
MTP014 | EM | Testing basal contact of western margin at top of W Conductor |
MTP015 | Geology | Longitudinal geological section through the neck of the Panhandle at top of the W Conductor, to confirm intrusive or extrusive related model of intrusion geometry, with implications for belt wide targeting |
MTP016 | Geology/EM | Following up on high grade result of remobilised sulphides in hole MTD006 0.25m at 3.8% Ni, 0.7% Cu and 0.7g/t PGE, up dip of NW2 Conductor and along northern margin of gravity high body |
MTP017 | EM | Discrete EM anomaly along margin of coincident gravity high body in unusual orientation on western margin of intrusion |
MTP018 | EM | Discrete EM anomaly on southern margin of the intrusion in highly favourable basal contact position |
MTP019 | Geology/EM | Testing down dip MTD003 intersection of 1m at 1.13% Ni and 0.49g/t Pd on the basal contact with coincident EM anomaly |
MTP020 | Geology | Testing down dip of hole MTD011 that showed multiple zones of nickel sulphide mineralisation |
MTP021 | EM | Testing up dip component of NW3 Conductor |
Table 1: Descriptions of the Mulga Tank Drill Targets
PANHANDLE AREA AND HOLE MTP021
The Company has recently completed additional interpretation and targeting work across the Panhandle and NW Sector of the MLEM survey. This work identifies four additional bedrock conductor targets within this area, with modelling focused on the mid-to-late EM channels.
Further targeting work at the high conductance NW3 Conductor shows shallower up dip components of the anomaly in the mid channels, these have been used to design an additional drill hole MTP021 to test this feature within the first phase of the drill program, expanding the planned initial program to ten holes.
Target | Aerial Size (m) | Conductance (S) | Depth to Top (m) | Comments |
NW1 Conductor | ~200x600m | ~500-750 | ~100-150m | Low to moderate conductance, steep NW-NNW dip 65-75 |
NW2 Conductor | ~400x750m | ~4,000-8,000 | ~500-550m | High conductance, moderate N dip 30-45, shallow NE plunge |
NW3 Conductor | ~1,000x1,000m | ~5,000-8,000 | ~550-600m | High conductance, shallow N dip 15-25 |
NW4 Conductor | ~400x600m | ~1,000-3,000 | ~175-200m | Moderate conductance, moderate NE dip 35-45 |
NW5 Conductor | ~500x800m | ~500-1,000 | ~150-200m | Moderate conductance, moderate NE dip 35-45 |
NW6 Conductor | ~200x400m | ~1,000-1,500 | ~125-150m | Moderate conductance, moderate-steep NE dip 50-60 |
NW7 Conductor | ~200x400m | ~750-1,250 | ~100-125m | Moderate conductance, steep NE dip 60-70 |
Figure 2: Mulga Tank MLEM mid-late channel CH30BZ image showing EM plates and WMG's planned drill holes
Table 2: Summary of Mulga Tank Panhandle area MLEM targets
COVER
DUNITEFOOTWALL
Figure 3: Section showing planned hole MTP021
WMG is excited to commence the Mulga Tank drilling program after the culmination of months of technical and preparation work. The Company looks forward to updating shareholders on its progress as this exciting drilling program develops.
For further information please contact:
Dr Caedmon Marriott Managing Director Tel: +61 475 116 798
Email:contact@westernmines.com.au
This announcement has been authorised for release to the ASX by Dr Caedmon Marriott, Managing Director
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Western Mines Group Ltd. published this content on 19 April 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 19 April 2022 22:54:03 UTC.