Vår Energi ASA provided an update on the progress for the Balder X development and a revised cost estimate which reflect increased scope of work, the continued impact from global supply chain challenges, Covid-19 and schedule change. The Company's production target of more than 350,000 boed by the end of 2025 is unaffected. Balder X, which comprises Balder Future and the Ringhorne Phase IV drilling projects, is set to extend production from the Balder Hub to 2045 and support development of new nearby discoveries by upgrading existing infrastructure and drilling of new wells.

A baseline project review has identified additional gross investment requirements of USD 1.2 billion (NOK 11.5 billion), bringing the total estimated gross project cost to USD 4.3 billion (NOK 40.7 billion). First oil from Balder X is now expected in the third quarter of 2024, compared to previously late in 2023. The revision will not impact the 2022 CAPEX guidance and the Company maintains its dividend guidance for 2022 and long-term dividend policy.

The main production impact from the revised schedule is expected in 2024, however partly mitigated by a faster ramp-up of production as more Balder Future production wells are expected to be ready for start-up. The Company also expects the majority of incremental capital expenditure to be incurred in 2024. The new cost estimate and schedule change are mainly related to Balder Future, with increased scope and additional engineering and construction work on the Jotun FPSO lifetime extension.

External factors including Covid-19, challenging weather conditions for drilling and offshore activities, and commodity and services price inflation have to some extent impacted the overall project. Key focus areas are to ensure progress and cost control for the remaining part of the project. Balder X is expected to unlock an estimated 143 million barrels of recoverable reserves.

Once the Jotun FPSO is re-installed and connected to the Balder Future production wells, it will tie in the new Ringhorne wells. Furthermore, the King and Prince discoveries announced in 2021, estimated to hold additional 60-135 million barrels of oil, are being considered for tie-ins to the Jotun FPSO. Vår Energi is also evaluating new exploration prospects in the highly prolific Balder area.

The revised cost estimate and schedule will be included in Norway's National Budget for 2023 to be published 6 October 2022. The Balder X Project: The Balder field is in production license PL 001 - the very first license on the Norwegian Continental Shelf (NCS) - acquired in 1965; The Balder X project aims to extend production to 2045 and consists of four ongoing projects: Balder FPU life extension - vessel upgrade, drilling new wells on Ringhorne III/IV and Balder Future including Jotun FPSO lifetime extension and drilling 14 new production wells and one water injection well; The project is reusing existing infrastructure to reduce the development footprint and to open for a potential future retirement of production assets which may reduce annual CO2 emission 100,000 ton per year; King and Prince discoveries in the Balder area, estimated to hold 60-135 million barrels of oil, are currently assessed for tie-ins to the Jotun FPSO; License owners: Vår Energi ASA 90% and Mime Petroleum AS 10%.