Gascoyne Resources Limited announced that it has executed a long term LNG fuel supply agreement with EVOL. The locally sourced LNG provides the lowest cost and lowest emissions fuel solution for Dalgaranga's power generation needs. Another significant advantage is that LNG will be used in the project's 2.5Mtpa gold processing facility to fuel its carbon regeneration kiln, elution boiler and bullion furnace, reducing the cost and complexity of multiple fuel sources within the plant. Construction of the LNG facilities and Zenith Pacific's 15MW power station has commenced and is on schedule for completion prior to the commissioning of the 2.5 Mtpa processing plant which is on track for May this year ­ in approximately 4 months time.