Mosman Oil and Gas Limited provided an update on its Stanley project in the US (34.85% to 38.5% WI) and Cinnabar project (75% WI). Due to daily production variances, the Company's policy is to provide quarterly production updates unless there is a material change. Stanley Project (34.85% to 38.5% WI): Oil production at the Stanley-5 well has been restored by a successful workover, with initial flow rates similar to previous flow rates of circa 30-45 bopd (gross) from this well.

Stanley-5 had been shut in since 5 March. As previously announced, Stanley-3 was recompleted and placed back on production in April 2024. This well is producing both oil and gas.

The oil flow rate has increased to over 100 bopd (last 5 days) with the gas flow rates having declined since the recompletion. The overall effect is a significant increase in oil and gas production at Stanley compared to the March quarter. The 5 day gross average flow rates from the Stanley project have been approximately 150 bopd and 169 mcfd (aggregate gross circa 180 boepd).

Cinnabar Project (75% WI): The Cinnabar-1 (G3) well has now been recompleted and wellhead pressure rose to 1950 psi. This well has initially flowed oil and gas but has not yet established continuous flow. This may have confirmed the need for artificial lift to optimize production.

The Company will provide details of production at all assets as part of its June 2024 quarter update.