Kalium Lakes Limited provides update on Beyondie Sop Project. Key commissioning milestones include: Hydro and vacuum tests on cooling crystalliser successfully complete; Hydro testing through flotation successfully complete; Water commissioning of process loop circuits underway - fire, raw, gland, potable and process water headers successfully commissioned; The gas power station now operating continuously, with all switchrooms and transformers energised; Harvesting of potassium salts continues on schedule; Construction activities and parallel commissioning activities remain within the capital expenditure budget; and Several key equipment vendors attending site to support commissioning activities. SOP purification plant highlights include commencement of water commissioning of key vessels and process piping loop circuits, with successful completion of hydro testing on the cooling crystalliser and flotation circuits. Vacuum testing on the cooling crystalliser has also been successfully completed while insulation of the cooling crystalliser and conditioning vessels continues. The gas power station is now operating continuously, ensuring that sufficient power is available for all commissioning requirements moving forward. All high voltage equipment on site has been energised, substantially de-risking the Project. Instrumentation commissioning is progressing in the crushing, flotation and crystallisation areas, with trial running of the plant feed conveyor completed successfully.