Kalium Lakes Limited (KLL) has announced the completion of more significant milestones, with the overall Beyondie SOP Project (BSOPP) approaching 70% complete, on budget and on schedule.

These include the practical completion of the 79.4 km BSOPP natural gas lateral which is fully owed by Kalium Lakes, as well as the commencement of installation of steel and key mechanical equipment for the SOP purification plant.

CEO, Rudolph van Niekerk, said: 'Overall we are close to achieving 70% project completion and importantly we remain on schedule and on budget.

'Practical completion of our gas pipeline allows us to finalise the gas supply infrastructure and significantly de-risks completion of construction for this part of the Project.

'At the same time, we are pleased to see the good progress made in construction of the SOP purification plant, with commencement of steel and mechanical equipment tracking on schedule,' he said.

The natural gas pipeline, which runs from the inlet station at the Goldfields Gas Pipeline (GGP) interface near the Great Northern Highway to the tie-in at the delivery station near the SOP purification plant, has achieved practical completion by Pipecraft three weeks ahead of schedule and under budget. Environmental rehabilitation work is well underway and Pipecraft demobilisation is now planned for early November.

APA has now mobilised to site to commence construction of the metering facility and tie-in to the GGP. As the hot tap is already in place, this work is forecast to be completed in the next month.

Construction of the gas inlet and delivery stations will commence with Primero mobilising to site. When these stations are completed, Primero and APA will work together to commission the infrastructure that will enable gas supply for power generation and SOP processing.

Evaporation pond construction continues ahead of schedule and liner installation is also accelerating with three liner installation contractors now operating at site.

Construction work at the SOP Purification plant is progressing on budget and schedule, with concrete works now more than 35% complete. Erection of structural steel and installation of key process equipment has commenced.

Delivery of key equipment for the SOP plant continues on schedule, with many items now received at site and the delivery of all key equipment forecast to be completed by the end of 2020.

Forward looking statements

Certain information in this document refers to the intentions of Kalium Lakes, but these are not intended to be forecasts, forward looking statements or statements about the future matters for the purposes of the Corporations Act or any other applicable law. The occurrence of the events in the future are subject to risk, uncertainties and other actions that may cause Kalium Lakes' actual results, performance or achievements to differ from those referred to in this document. Accordingly, Kalium Lakes and its affiliates and their directors, officers, employees and agents do not give any assurance or guarantee that the occurrence of these events referred to in the document will actually occur as contemplated. Statements contained in this document, including but not limited to those regarding the possible or assumed future costs, performance, dividends, returns, revenue, exchange rates, potential growth of Kalium Lakes, industry growth or other projections and any estimated company earnings are or may be forward looking statements. Forward-looking statements can generally be identified by the use of words such as 'project', 'foresee', 'plan', 'expect', 'aim', 'intend', 'anticipate', 'believe', 'estimate', 'may', 'should', 'will' or similar expressions. These statements relate to future events and expectations and as such involve known and unknown risks and significant uncertainties, many of which are outside the control of Kalium Lakes. Actual results, performance, actions and developments of Kalium Lakes may differ materially from those expressed or implied by the forward-looking statements in this document. Such forward-looking statements speak only as of the date of this document.

There can be no assurance that actual outcomes will not differ materially from these statements. To the maximum extent permitted by law, Kalium Lakes and any of its affiliates and their directors, officers, employees, agents, associates and advisers: disclaim any obligations or undertaking to release any updates or revisions to the information to reflect any change in expectations or assumption; do not make any representation or warranty, express or implied, as to the accuracy, reliability or completeness of the information in this document, or likelihood of fulfilment of any forward-looking statement or any event or results expressed or implied in any forward-looking statement and disclaim all responsibility and liability for these forward-looking statements (including, without limitation, liability for negligence).

Contact:

Tel: +61 (0)8 9240 3200

Email: info@kaliumlakes.com.au

(C) 2020 Electronic News Publishing, source ENP Newswire