ONEOK, Inc. announced plans to expand its pipeline capacity connecting Mid-Continent and Gulf Coast refined products supply with the greater Denver area to meet growing demand and increase connectivity with Denver International Airport (DIA). The project includes construction of a new 230-mile, 16-inch diameter pipeline from Scott City, Kansas, to DIA and the addition or upgrading of certain pump stations along the existing refined products pipeline system. Total system capacity will increase by 35,000 barrels per day (bpd) and will have additional expansion capabilities.
The project is expected to cost approximately $480 million and be completed in mid-2026. Following the close of an open season earlier this year, the project is fully subscribed under long-term contracts.